Active Bond Projects

2008 Proposition 3 : Drainage Improvements on Town Creek

Bond Amount: $9,200,000
Bond Issued: 2011 General Obligation Bonds ($5,500,000) and 2013 General Obligation bonds ($3,700,000)
Description: This bond was passed back in 2008 in order to help lessen storm water runoff impacts of upstream developments.
Update : Utility conflicts are being addressed and plans are being completed for utility relocation efforts. Drainage and roadway R.O.W. acquisition has begun. Final design received in March 2019. Project is scheduled to bid in Fall 2020, upon acquisition of easements 

 

2014 Proposition 2 : Fire Station 3 

Fire Station 3Bond Amount: $4,000,000
Bond Issued: 2015 General Obligation bonds Issues ($500,000)  2018 General Obligation Bonds ($3,500,000)  
Description: This bond was passed to fund the construction of Fire Station #3 located at Wiedner and FM 1003. This bond also included the purchased of the city's first ladder truck.
Update : Ladder truck was delivered on November 2017. Construction Project went out to bid July 2020. Fire Station #3 is expected to be open for service in October 2021.

 

2014 General Obligation Bond: FM 1103 Reconstruction Project

Bond Amount: $7,000,000
Bond Issued: 2015 General Obligation Bonds  ($1,000,000) and 2019 General Obligation Bonds  ($6,000,000)
Description: This bond was issued in order to allow the City to pay a portion of the associated with the TxDOT reconstruction project.
Update : Construction is expected to begin early 2021. (All project dates are set by TxDOT)

 

2018 Proposition A : City facilities expansion
City Hall Annex

Bond Amount: $2,450,000
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued to allow for the city to expand the existing Public Works building and to remodel an old school building donated by SCUCISD that will provide additional office space to be used by City Staff currently located at City Hall.
Update : Design work on the City Hall annex started late 2019. Construction started July 2020. Expected to be completed in spring of 2021. Public works expansion plans started late 2019. No construction timeline at the current time. 

 

2018 Proposition B : Public Safety Radio Communications

Bond Amount: $450,000
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued to allow for the city to enter into an agreement with LCRA to install new radio transmitters and antennas on the City of Cibolo Water tower located off of Main Street. The installation of new radio communication equipment to the water tower located at the sports complex will significantly increase and enhance the radio coverage within the City of Cibolo and surrounding communities.
Update : The work for this project has been completed September 2020.

 

2018 Proposition C : Tolle Road Reconstruction and Drainage Improvements

Bond Amount: $1,100,000
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued in order to help fix up Tolle Road Drainage.
Update : On 3/24/2020 the City of Cibolo entered into agreement with LAN engineering firm to provide 30% design engineering services. Construction estimated to begin 1/15/2021. 

 

2018 Proposition D : Tolle Park and the Miracle League Field

Bond Amount: $750,000
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued to allow for the city to build a Miracle League Field and start work on Tolle Park.
Update : Initial project scoping for Tolle Park was started October 2019. The Miracle League Field is entering initial design phase. Fundraising activities through the YMCA are ongoing.. 

 

Revenue Bonds

Utility Revenue: 

Bond Amount: $1,500,000 
Bond Issued: 2019 Certificates of Obligation
Description: Issued to help pay for a utility line relocation in support of the TxDOT FM 1103 road expansion.
Update : Engineering work completed. Right of way acquisition completed. Project entered the construction phase December 2019. Project completed August 2020.

Road Improvements:

Bond Amount: $5,000,000
Bond Issued: 2019 Certificates of Obligation
Description: Issued to help pay for road and drainage improvements of Bolton and Santa Clara Rd to help support economic development.
Update : Santa Clara Drainage Improvements Construction started on 6/15/2020. Bolton Rd Santa Clara Rd Improvement Construction started on 713/2020. Both projects expected to be completed by late December 2020.