This is an update on the closure of Haeckerville Road. As the attached map depicts, Texas Sterling Construction will be closing Haeckerville Road, just south of Schaefer Road thru Arizpe Road. Local residents will retain access to their properties during this closure. They will be installing additional SWPPP devices and completing ROW clearing the remainder of this week and they are scheduled to begin milling asphalt and excavation activities on Monday (see short schedule below).
7/13/2022 – Install traffic control and close roadway
7/14/2022 – Install LPCB for additional project protection
7/15/2022 – Begin clearing operations
7/18/2022 – Mill roadway
7/19/2022 – Begin excavation for the channel improvements
The highlighted yellow section of Haeckerville Road will be closed on Wednesday July 13, 2022, and is scheduled to remain closed until the new drainage channel is complete and a new bridge has been built. This is estimated to be approximately 12 to 14 months.