One free pre-application meeting with staff will be allowed to discuss the requirements/challenges for a project. Each additional meeting after will have a fee of $100.
Show All Answers
Contact Planning and Engineering Staff;
The Unified Development Code (UDC) is a document of all consolidated development related regulations including, but not limited to, subdivision regulations, design standards and zoning requirements;
The land development code of Cibolo is called the Unified Development Code (UDC). Any new developer may reference City of Cibolo’s interactive Zoning Map along with the Easy Zoning Guide for zoning verification, permissible/conditional uses with a Zoning classification, setbacks, impervious coverage, lot sizes and other;
Reference current Fee Schedule
Reference Unified Development Code (UDC) - Article 20.3
Reference Unified Development Code (UDC) - Article 20.1.9;
On submittal of a complete Plat package, the typical process of review takes 45 days.
An Amending, Development and/or Minor Plat may be proved administratively and typically take 30 days for review.
Any plat shall be prepared by a qualified professional Engineer or registered Land Surveyor. City staff may make no recommendations of any one firm but may present a list of Engineers and/or Surveyors that have done or are doing work in the City, available upon request.
When requesting a new address for a construction development you need to contact the Fire Marshal of Cibolo by phone or email. Phone: 210-566-7008 Email: lperry@cibolotx.gov;
In order to get an official address in Cibolo you must fill out an application with the Guadalupe County Road and Bridge Department.
The Owner/Developer must submit a tree affidavit or a tree preservation plan with their preliminary plat or development site plan. Unified Development Code (UDC) Article 17.