Translate
Share
Print
Font Size

Active Bond Projects


2008 Proposition 3: Drainage Improvements on Town Creek

Bond Amount: $9,200,000
Expected Funding Available in FY 2021: $7,207,802
Bond Issued: 2011 General Obligation Bonds ($5,500,000) and 2013 General Obligation bonds ($3,700,000)
Description: This bond was passed back in 2008 in order to help lessen storm water runoff impacts of upstream developments.
Update: Utility conflicts are being addressed and plans are being completed for utility relocation efforts.  Drainage and roadway R.O.W. acquisition has begun. Final design was received in March 2019. Phase 1 of the project is scheduled to bid Winter 2021, upon acquisition of remaining easements.

2014 Proposition 2: Fire Station 3

Document - Copy (2)Bond Amount: $4,000,000
Expected Funding Available in FY 2021: $2,445,265
Bond Issued: 2015 General Obligation bonds Issues ($500,000)  2018 General Obligation Bonds ($3,500,000)  
Description: This bond was passed to fund the construction of Fire Station #3 located at Wiedner and FM 1003. This bond also included the purchased of the city's first ladder truck.
Update: Ladder truck has been delivered as of November 2017.  Bonds to be issued summer of 2019. Construction Contract awarded October 2020. Construction started December 2020. Projected to enter service November 2021.

2014 General Obligation Bond: FM 1103 Reconstruction Project

Bond Amount: $7,000,000
Expected Funding Available in FY 2021: $6,164,957
Bond Issued: 2015 General Obligation Bonds  ($1,000,000) and 2019 General Obligation Bonds  ($6,000,000)
Description: This bond was issued in order to allow the City to pay a portion of the associated with the TxDOT reconstruction project.
Update :Construction is expected to begin Late Summer 2021 (all project dates are set by TxDOT). 

2018 Proposition A: City facilities expansion
Document - Copy
Bond Amount: $2,450,000
Expected Funding Available in FY 2021: $2,513,534
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued to allow for the city to expand the existing Public Works building and to remodel an old school building donated by SCUCISD that will provide additional office space to be used by City Staff currently located at City Hall.
Update : Design work on the City Hall annex started late 2019.  
    • Architect Architexas Approved 5/28/2019
    • CMARJC Stoddard Approved 2/25/2020 
    • Abatement and demo work completed. 
    • Guarantee Maximum Price Due 3/23/2021
    • Est Construction begin 4/15/2021 
    • Est Construction Completion 12/31/2021
    • Public works expansion plans started late 2019.Construction scheduled for early 2021.
2018 Proposition C: Tolle Road Reconstruction and Drainage Improvements

Bond Amount: $1,100,000
Expected Funding Available in FY 2021: $914,842
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued in order to help fix up Tolle Road Drainage. Tolle Road and Drainage Improvements City Funds to be matched with funds from Steele Creek Developer through a Public Improvement Agreement.
Update : LAN approved to provide 30% design engineering services 5/24/2020 
Construction estimated to begin 6/15/2021

2018 Proposition D: Tolle Park and the Miracle League Field

Bond Amount: $750,000
Expected Funding Available in FY 2021: $750,000
Bond Issued: 2019 General Obligation Bonds 
Description: This bond was issued to allow for the city to build a Miracle League Field and start work on Tolle Park.
Update: Initial project scoping for Tolle Park was started October 2019.  Project is in initial design phase - Fall 2020.  Trail construction expected Spring/Summer 2021.

The Miracle League Field initial design work started Fall 2020.Fundraising activities through the YMCA are ongoing. Construction expected to start Spring 2021.

Revenue Bonds

Utility Revenue:
Bond Amount: $8,000,000
Expected Funding Available in FY 2021: $3,003,125
Bond Issued: 2012 Revenue Bonds
Description: Issued to help pay for a Sanitary Sewer system expansion -FM 78 East.Includes new regional sanitary sewer lift station. 
Update : Contract awarded September 2020 and construction started November 2020.

Road Improvements:

Bond Amount: $5,000,000
Expected Funding Available in FY 2021: $4,661,245
Bond Issued: 2019 Certificates of Obligation
Description: Issued to help pay for road and drainage improvements of Bolton and Santa Clara Rd to help support economic development.
Update: Santa Clara Drainage Improvements Construction completed. Bolton Rd & Santa Clara Rd Improvement Project under construction. Estimated Completion Date is 6/15/2021.

Bond Amount: $7,500,000
Expected Funding Available in FY 2021: $7,500,000.
Bond Issued: 2020 Certificates of Obligation
Description: Issued to help pay for road maintenance projects. This includes Cibolo Valley Drive from Old Wiederstein Road to Everyday Way.Additional projects to be assigned by City Council
Update : Work on Cibolo Valley Drive is expected to begin Spring 2021.Additional pavement maintenance projects also scheduled to start late Spring 2021.