Street closures for construction activities or events are listed weekly. Road projects affecting streets and sidewalk closures for 3 days or longer are listed below and removed when the road is reopened. Emergency road closures will be reported in real-time during situations like flooding or icy roads. 

Visit TxDot's Drive Texas map for a real-time update on Texas roads and highways.

IH 10 Expansion Project
Intermittent Closures at Santa Clara Rd starting July 7, 2023 at 8 PM through July 10, 2023 at 5 AM. Intermittent full closures for the East Bound Main Lanes (EBML), West Bound Main Lanes (WBML), East Bound Frontage Road (EBFR), and the West Bound Frontage Road (WBFR). Traffic will use Bolton Rd. Travel through the corridor is discouraged, and alternate routes are advised.

I-35 Northeast Expansion (I-35 NEX) Central Construction Project (provided by TxDot)

Speed limits have been reduced to 55 mph through the entire I-35 NEX Central project limits while the project is under construction. 

FM 3009 to FM 1518
Southbound

  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes and entrance ramp closure of I-35 from Roy Richard Drive to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next entrance ramp.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Schertz Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should follow signs to next available ramp.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road, exit ramp closure, and entrance ramp closure of I-35 from Roy Richard Drive to Schertz Parkway for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Wednesday, July 5, until Saturday, July 8, 12:00 PM to 12:00 AM. Right lane closure on southbound frontage road of I-35 from FM 2252 to Cibolo Valley Drive and rolling closures on southbound mainlanes of I-35 from Cibolo Valley Drive to Pat Booker Road for beam staging.

FM 1518 to Loop 1604

Northbound

  • Sunday, July 2, 9:00 PM to 5:00 AM. Full closure of northbound frontage road of I-35 from Loop 1604 to Forum Parkway for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound I-35 mainlanes from Forum Parkway to Evans Road for striping, barrier, and temporary pavement work.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road, exit ramp closure, and entrance ramp closure on I-35 from Forum Parkway to Evans Road for striping, barrier, and temporary pavement work. Traffic should use next exit and entrance ramps.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on northbound frontage road of I-35 at Forum Parkway for striping, barrier, and temporary pavement work.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Full closure of northbound frontage road of I-35 from Loop 1604 to Forum Parkway for striping, barrier, and temporary pavement work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on northbound I-35 mainlanes from Forum Parkway to Evans Road for striping, barrier, and temporary pavement work.
  • Wednesday, July 5, until Friday, July 7, 9:00 PM to 5:00 AM. Left lane closure on northbound frontage road of I-35 from Forum Parkway to Agora Parkway for pothole work. 

Southbound

  • Through Sunday, August 13, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for temporary pavement, striping, barrier, column, and cap work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for temporary pavement, striping, and barrier work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes and entrance ramp closure of I-35 from Retama Parkway to Forum Parkway for striping work. Traffic should use next entrance ramp.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Traffic shift to the left on eastbound Evans Road and alternating lane closures on southbound frontage road of I-35 at Evans Road for temporary pavement work.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes, exit ramp closure, and entrance ramp closure of I-35 from Corporate Drive to Olympia Parkway for striping, barrier, and temporary pavement work. Traffic should use prior exit ramp.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Southbound I-35 entrance ramp closure from Old Austin Road to Forum Parkway for striping and barrier work. Traffic must use the Forum Parkway turnaround and follow detour signs to access southbound I-35.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound I-35 mainlanes from Forum Parkway to Ferrell Road for striping, barrier, and temporary pavement work.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Full closure on southbound frontage road of I-35 from Old Austin Road to Forum Parkway for temporary pavement, striping, and barrier work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 from Olympia Parkway to Gateway Boulevard for bridge foundation, temporary pavement, striping and barrier work.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating lane closures on southbound frontage road of I-35 from Evans Road to Olympia Parkway for bridge foundation, striping, barrier work, and temporary pavement work.

Loop 1604 Interchange
Northbound

  • Sunday, July 2, 9:00 PM to 5:00 AM. Full closure on northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
  • Sunday, July 2, 9:00 PM to 5:00 AM. Northbound I-35 to westbound Loop 1604 connector ramp closure for striping and barrier work. Traffic should follow the detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Full closure on northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Northbound I-35 to westbound Loop 1604 connector ramp closure for striping and barrier work. Traffic should follow the detour signs.
  • Wednesday, July 5, until Saturday, July 8, 9:00 PM to 5:00 AM. Eastbound Loop 1604 to northbound I-35 connector ramp closure for striping and barrier work. Traffic should follow detour signs.

Southbound

  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Multiple lane closures (3) on southbound mainlanes, exit ramp closure, and entrance ramp closure of I-35 from Corporate Drive to Olympia Parkway for striping, barrier, and temporary pavement work. Traffic should use prior exit ramp.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Alternating ramp closures on southbound I-35 connector ramp to Pat Booker Road for striping, barrier, and bridge substructure work. Traffic must exit Loop 1604 (exit 172) and follow the detour signs to Pat Booker Road.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Eastbound Loop 1604 to southbound I-35 connector ramp closure for striping and barrier work. Traffic must exit at IKEA-RBFCU Parkway and follow the detour signs to southbound I-35.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Westbound Loop 1604 to southbound I-35 connector ramp closure for earthwork. Traffic must exit at Lookout Road and follow the detour signs to southbound I-35.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Southbound I-35 to eastbound Loop 1604 connector ramp closure for striping, barrier, and earthwork. Traffic must exit at westbound Loop 1604 and follow the detour signs to access eastbound Loop 1604.
  • Sunday, July 2, until Saturday, July 8, 9:00 PM to 5:00 AM. Southbound I-35 collector ramp closure at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic must use Loop 1604 (exit 172) to access southbound I-35 and follow detour signs.
  • Thursday, July 6, until Saturday, July 8, 9:00 PM to 5:00 AM. Westbound Loop 1604 collector to southbound I-35 connector ramp closure for barrier work. Traffic should follow the detour signs.

FM 1103 Construction (provided by TxDot)
  • FM 1103 at Gatewood Bay and Saddle Creek - The traffic pattern will shift to the south side near the entrances to Gatewood Bay and Saddle Creek Ranch neighborhoods. One lane in each direction will remain open while crews work on the north side of the road.
  • FM 1103 at Green Valley Road and Chelsea Drive - Pedestrian sidewalk ramps at Green Valley Road and Chelsea Drive will be closed until the intersections are reconstructed.
Sign up for the FM 1103 Construction Newsletter to have these updates sent to your inbox.